Comprising of mechanical works, piping network

Project Title

Comprising of mechanical works, piping network

Location
Badin
Client
B.P Pakistan
Project Details
Since 2002 Petrocon is continuously working as main contractor first for British Petroleum Pakistan until 2011 and now for United Energy Pakistan Limited after acquiring the field from B.P Pakistan in Badin Concession area. During this period Petrocon has constructed numerous wellhead assemblies comprising of mechanical works, piping network and E & I works, construction of oil / gas / water / compressed air high pressure pipelines including allied civil works, thrust bore and horizontal directional drilling crossing of canals / nullah and roads, construction and relocation of plant facilities and equipment including related civil and E & I works. For this purpose Petrocon is maintaining permanent setup at Tando Muhammad Khan equipped with required T & P, skilled / non skilled and management staff.
Salient Features of the works executed at Badin Concession area during the period from 2002 to date are elaborated hereunder:
Construction of Wellhead assemblies 102 Nos
Construction of carbon steel flow / trumk pipeline 2” dia to 12” dia 250 KM
Construction of HDPE pipeline 2” to 4” 35 KM
Construction of Fiber glass pipeline 2” to 4” 12 KM
Number of plant erection and Relocation job 35 Nos
Number and length of thrust bore crossing 17 Nos/ 750M
Number and length of Horizontal Directional drilling 135 Nos/ 10,000M

Navigate Your Engineering Challenges - Book Your Consultation Now!